|
|
TENDER NOTICE NO.
SGW272_156_T1_22A
|
|
Corrigendum &
addendum No.1 against tender No.SGW272_156_T1_22A
on behalf of the President of India for "Design,
Supply, Installation, testing & commissioning of indoor & out
door & signaling equipments for panel interlocking work at
Kalipahari & Panagarh (W) station in Asansol Division of Eastern
Railway on Risk & cost measure."
|
|
In the above
mentioned tender read as under:-
|
|
1. |
Earnest money
deposit is Rs.1,55,780.00 in stead of Rs.50,000.00 and no Standing
Earnest Money.
|
|
2. |
| Existing
tender |
Amended
tender |
| Para 6.0
to 6.2 of GCT to be deleted |
|
6.0 |
EARNEST
MONEY:
|
|
6.1 |
The tender
shall deposit in favour of the financial advisor & chief
account officer (con), Eastern Railway, kolkata-700 001, the
desire earnest money as given in para-3 of Instruction To
Tenderer.
|
|
|
1) The
tenderer shall be required to deposit Earnest Money with the
tender for the due performance with the stipulation to keep
the offer open till such date as specified in the tender,
under the condition of tender. The Earnest Money shall be 2%
of the estimated tender value as indicated in the tender
notice. The Earnest Money shall be rounded to the nearest
Rs.10/-. The Earnest Money shall be applicable for all modes
of tenders.
|
|
|
2) The
Earnest Money should be in cash or in any of the following
forms:- |
|
|
i) Deposit
Receipts, pay order, Demand Drafts, These forms of Earnest
Money could be either of the State Bank of India or of any
of the nationalized Banks. No confirmatory advice from the
Reserve Bank of India will be necessary. |
|
|
ii) Deposit
receipts executed by the scheduled banks ( other than the
State Bank of India and the Nationalized Banks) approved the
Reserve Bank of India for this purpose. The Railways will
not, however, accept deposit receipt without getting in
writing the concurrence of the Reserve Bank of India.
|
|
| Para 8.0
to 8.1 of GCT to be deleted |
|
8.0 |
SALES
TAX/WB VAT RULES-2005 CLEARANCE CERTIFICATE :
|
|
8.1 |
The tender
should be accompanid by the upto-date sales Tax/WB VAT Rules
– 2005 clearance certificate in form xxxvii issued by
appropriate commercial Tax Officer in favour of the tenderar.
No payment will be released to the contractor till the STCC
is submitted and the contractor shall have no claim in this
regard for non payment of work done in absence of such
certificate.
|
|
| Para 12.0
to 12.4 of GCT to be deleted |
|
12.0 |
SECURITY
DEPOSIT :
|
|
12.1 |
Total
amount of Security Deposit of the fulfillment of the
contract will be as under :-
|
|
12.2 |
The
Earnest Money deposit by the contractor with his tender will
be retained by the Railway as part of security for the due
and faithful fulfillment of the contract by the contractor.
The balance to make up the security deposit, the rate for
which are given below, may be deposited by the contractor in
cash or may be recovered by percentage deduction from the
Contractor’s "on account" bills. Provided also
that in case of defaulting contractor the Railway may retain
any amount due for payment to the contractor on the pending
"on account bill" so that the amount so retained
may not exceed 10% of the total value of the contract.
|
|
|
Unless
otherwise specified in the special condition, if any, the
Security Deposit/rate of recovery/mode of recovery shall be
as under :-
|
|
(a) |
Security deposit for each
work should be 5% of the contract value. |
|
(b) |
The rate
of recovery should be at the rate of 10% of the bill amount
till the full security deposit is recovered. |
|
(c) |
Security
deposit will be recovered only from the running bills of the
contract and no other mode of collecting SD such as SD in
the form of instruments like BG, FD, etc. shall be accepted
towards Security Deposit.
|
|
|
Security
Deposit shall be returned to the contractor after the
physical completion of the work as certified by the
Complement Authority. The Compliment Authority shall
normally be the authority who is complement to sign the
contract. If this competent Authority is of the rank lower
than JA grade, then a JA grade officer (concerned with the
work) should issue the certificate. The certificate, inter
alia, should mentioned that the work has been completed in
all respects and that all the contractual obligation have
been fulfilled by the contractor and that there is no due
from the contractor to Railways against the contract
concerned. Before releasing the SD, an unconditional and
unequivocal no claim certificate from the contractor
concerned should be obtained.
|
|
Note:- No
interest will be payable upon the Earnest money and security
deposit or amount payable to the contractor under the
contract, but Government Security Deposit in terms of sub
clause (1) of this clause will be payable with interest
accrued thereon. The practice of allowing Standing Earnest
Money Deposit is dispensed with.
|
|
| Para 18.0
to 18.1 of GCC to be deleted. |
|
18.0 |
ISSUE OF
MATERIALS FROM RAILWAY STORES :
|
|
18.1 |
Any
material, which the contractor would normally have arranged
for himself, is supplied by the Railway either at contractor’s
request or suomoto in order to prevent any possible delay in
the execution of the work likely to occur due to contractor’s
inability to make adequate arrangement for supply thereof or
otherwise.
|
|
|
Recovery of
prices of such materials will be made from the next
immediate ‘running’ or ‘on account’ bill of the
contracting agency at the highest of the following rates:
|
|
|
i) |
Book rates
or last purchase or market rate whichever is higher |
Plus 5% on
account of initial freight , 2% on account of incidental
charges & 12.5% towards departmental charges on the
overall cost. |
|
|
ii) |
Accepted
tender rate for such material under contract.
|
|
|
|
Fright
between Railway source of supply and the Railway store/depot
shall be to the contractor’s account.
|
|
|
If
prevailing market rates are not available, the recovery
rates may be worked out by escalating the last purchase rate
@10% escalation per annum.
|
|
| Para 30.0
to 30.2 of GCC to be deleted. |
|
30.0 |
RESCINDING
OF CONTRACT :
|
|
30.1 |
1.
Determination of contract owing to default of contractor –(1)
if the contractor should ……
|
|
|
(i) |
Becomes
bankrupt or insolvent, or |
|
|
(ii) |
Make an
arrangement with of assignment in favour of his creditors,
or agree to carry out the contract under a Committee of
Inspection of his creditors, or |
|
|
(iii) |
Being a
Company or Corporation, go into liquidation (other than a
voluntary liquidation for the purpose of amalgamation or
reconstruction), or |
|
|
(iv) |
Have an
execution levied on his goods or property on the works, or |
|
|
(v) |
Assign the
contract or any part thereof otherwise than as provided in
clause 7 of these conditions or |
|
|
(vi) |
Abandon the
contract, or |
|
|
(vii) |
Persistently
disregard the instructions of the engineer, or contravene
any provision of the contract, or |
|
|
(viii) |
Fail to
adhere to the agreed programme of work by a margin of 10% of
the stipulated period, or |
|
|
(ix) |
Fail to
remove materials from the site or to pull down and replace
work after receiving from the Engineer notice to the effect
that the said materials or works have been condemned or
rejected under Clause 25 and 27 of these conditions, or |
|
|
(x) |
Fail to
take steps to employ competent or additional staff and
labour as required under Clause 26 of the condition, or |
|
|
(xi) |
Fail to
afford the Engineer’s or Engineer’s representative
proper facilities for inspecting the work or any part
thereof as required under Clause (28) of the condition, or |
|
|
(xii) |
Promise,
offer or give any bribe, commission, gift or advantage
either himself or through his partner, agent or servant to
any officer or employee of the Railway or to any person on
his or on their behalf in relation to the execution of this
or any other contract with this Railway, |
|
|
(xiii) |
(A) At any
time after the tender relating to the contract has been
signed and submitted by the contractor, being a partnership
firm admit as one of its partners or employ under it or
being an incorporated company elect or nominate or allow to
act as one of its directors or employ under it in any
capacity whatsoever any retired engineer of the gazetted
rank or any other retired gazeted officer working before his
retirement, whether in the executive or administrative
capacity, or whether holding any pensionable post or not, in
the Engineering Department of the Railways for the time
being owned and administered by the President of India
before the expiry of two years from the date of retirement
from the said service of such Engineer or Officer unless
such Engineer or Officer has obtained permission from the
President of India or any officer dully authorized by him in
this behalf to become a partner or a director or to take
employment under the contractor, as the case may be, or
|
|
|
(B) Fail to
give at the time of submitting the said under :- |
|
|
(a) |
The correct
information as to the date of retirement of such retired
engineer or retired officer from the said service, or as to
whether any such retired engineer or retired officer was
under the employment of the contractor at the time of
submitting the said tender, or |
|
|
(b) |
The correct
information as to such engineers or officers obtaining
permission to take employment under the contractor or |
|
|
(c) |
Being a
partnership firm, the correct as to, whether any of its
partners was such a retired engineer or a retired officer,
or |
|
|
(d) |
Being an
incorporated company, correct information as to whether any
of its directors was such a retired engineer or a retired
officer, or |
|
|
(e) |
Being such
a retired engineer or retired officer suppress and not
disclose at the time of submitting the said tender the fact
of his being such a retired engineer or a retired officer or
make at the time of submitting the said tender a wrong
statement in relation to his obtaining permission to take
the contract or if the contractor be a partnership firm or
an incorporated company to be partner or director of such
firm or company as the case may be or to seek employment
under the contractor, and after expiry of 48 hours notice, a
final termination notice (Proforma as Annexure V) should be
issued.
|
|
Then and in
any of the said clause, the engineer on behalf of the
Railway may serve the contractor with a notice (Proforma at
Annexure iii) in writing to that effect and if the
contractor does not within seven days after the delivery to
him to such notice proceed to make good his default in so
far as the same is capable of being made good and carry on
the work or comply with such directions as aforesaid to the
entire satisfaction of the Engineer, the Railway shall be
entitled after giving 48 hours notice (Proforma at Annexure
iv) in writing under the hand of the Engineer to rescind the
contract as a whole or in part of parts (as may be specified
in such notice).
|
|
2) Right of
Railway after rescission of contract owing to default of
Contractor – in the event of any or several of the
courses, referred to in sub-clause (1) of this clause, being
adopted:-
|
|
(a) |
The
contractor shall have no claim to compensation for any loss
sustained by him by reason of his having purchased or
procured any materials or entered into any commitments or
made any advances on account of or with a view to the
execution of the works or the performance of the contract
and contractor shall not be entitled to recover or be paid
any sum for any work there to for actually performed under
the contract unless and until he Engineer shall have
certified the performance of such work and the value payable
in respect thereof and the contractor shall only be entitled
to be paid the value so certified.
|
|
(b) |
The
Engineer or the Engineer’s representative shall be
entitled to take possession of any materials, tools,
implements, machinery & buildings on the work or on the
property on which these are being or out to have been
executed and to retain and employ the same in the further
execution of the works of any part thereof until the
completion of the works without the contractor being
entitled to any compensation for the use and employment
thereof or for wear and tear pr destruction thereof.
|
|
(c) |
The
Engineer shall as soon as may be practicable after removal
of the contractor fix and determined ex-parte or by or after
reference to the parties or after such investigation or
enquiries as he may consider fit to make or institute and
shall certify what amount (if any) had at the time of
rescission of the contract been reasonably earned by or
would reasonably accrue to the contractor in respect of the
work then actually done by him under the contract and what
was the value of any unused, or partially used materials,
any constructional plant and any temporary works upon the
site.
|
|
The
legitimate amount due to the contractor after making
necessary deduction and certify by the Engineer should be
released expeditiously.
|
|
| Para 44.0
to 44.5 of GCC to be deleted |
|
44.0 |
EXECUTION
OF NON-SCHEDULED ITEMS OR VARIATION OF QUANTITIES OF THE
SCHEDULES BEYOND 25% :
|
|
|
For the
variation of quantities beyond +25% of the agreemental value
the rates will as follow :
|
|
44.1 |
For the
first 15% increase in the value beyond 25% of the
agreemental value, the rate will be reduce by 2% in the
incremental value of the agreement.
|
|
44.2 |
For next
10% increase in the value, rate will be further reduce by 2%
(i.e. total 4%) for the further incremental value of the
agreement.
|
|
44.3 |
For
increase beyond +50% of agreemental value (if any) can be
done only in exceptional cases after negotiating fresh
rates.
|
|
|
44.1,44.2 &
44.3 will be binding to the tenderer |
|
44.4 |
However,
the Railway reserved the right to execute value of work over
agreemental value in best and most economical manner as may
consider fit, by other agency.
|
|
44.5 |
No claim
whatsoever will be entertained in this matter and decision of
railway under clause.
|
|
44.6 |
If it is
considered necessary that the item of works included in
Schedule would not cover all works involved in the execution
of the work, additional item of work which are considered
necessary and unit price of such item shall be given
separately along with Explanatory Notes.
|
|
44.7 |
If during
the execution of the works the contractor is called upon to
carry out any new item of work not included in accepted
Schedule and subsequent addition /alteration if any, it
should not be executed before a rate has been agreed to by
the Railway in the manner as indicated in the General
Condition of Contract.
|
|
44.8 |
The
quantities quoted in the Schedule are not firm and may be
varied at the time of awarding of the Contract.
|
|
| Para 8.0
to 8.2 of SCC to be deleted. |
|
8.0 |
WORKS
PERFORMANCE GUARANTEE :
|
|
8.1 |
The
procedure for obtaining performance guarantee is outline
below :-
|
|
(a) |
The
successful bidder should give a Performance Guarantee in the
form of an irrevocable bank guarantee amounting to 5% of the
contract value. |
|
(b) |
The
Performance Guarantee should be furnished by the successful
contractor after the letter of acceptance has been issued,
but before signing of the agreement and should be valid up
to expiry of the maintenance period. The agreement should
normally be signed within 15 (fifteen) days after the issue
of LOA and Performance Guarantee should also be submitted
within this time limit. |
|
(c) |
Performance
Guarantee hall be released after satisfactory completion of
the work and maintenance period is over. The procedure for
releasing should be same as for Security Deposit. |
|
(d) |
Wherever
the contract are rescinded, the security deposit should be
forfeited and the Performance Guarantee hall be encashed and
the balance work should be got done separately. |
|
(e) |
The
balance work shall be got done independently without risk
and cost of the original contractor. |
|
(f) |
The
original contractor shall be debarred from participating in
the tender for executing the balance work. If the failed
contractor is a JV or a partnership firm, then every
number/partner of such a firm would be debarred from
participating in the tender for the balance work either in
his/her individual capacity or as a partner of any other
JV/partnership firm.
|
|
| Para 3.0
to 3.2 of IIT to e deleted |
|
3.0 |
EARNEST
MONEY :
|
|
3.1 |
Earnest
Money against this tender is Rs.1,55,780.00 (Rupees
one lakh fifty five thousand seven hundred eighty )only. The
Earnest Money is to be submitted as per details given in
clause 6 of General Condition of Tender.
|
|
3.2 |
Validity of
Earnest Money to be at least up to the validity of the
offer.
|
|
| Forms
of tender Annexure-B |
GUARANTEE BOND FOR
SECURITY DEPOSIT
ABANDONED |
| Forms
of tender Annexure-C |
BANK GUARANTEE
(ON STAMP PAPER OF REQUISITE VALUE)
ABANDONED |
|
|
|
|
|
All
other terms & condition remain unchanged.
|
|
|
This notice is
available at www.tendertimes.com and www.easternrailway.gov.in |
Click
here to see the original tender
|
|
CHIEF SIGNAL & TELECOM. ENGINEER,
|
|
|
EASTERN RAILWAY,
|
|
|
FOR AND ON BEHALF OF THE PRESIDENT OF
UNION OF INDIA
|
|