Sub:
Tender notice for improvement of area of Building Berth
Western Side by hard standing/concreting etc. at GRSE Main.
|
|
You
are hereby requested to submit sealed quotation at Civil
Engineering Department, 43/46, Garden Reach Road, Kolkata-700
024 before 1400 Hrs on 15.01.2008 with your lowest rate
for the items as per attached schedule with the above work
under the following terms :-
|
| 1. |
Scope of Work
: Earth work in excavation, dressing & leveling
the area, providing & laying jhama for hard standing,
providing cement concrete, supplying tor steel reinforcement,
carriage of earth or dismantled bricks or concrete, placing
in position mild or tor steel reinforcement etc. as
per standard procedure and specification.
Click here
to download bid document
|
| 2. |
Earnest
Money: An earnest money in the form of demand draft
of Schedule Bank of Rs 12,000/- shall be submitted along
with the tender. This earnest money will be part of the
security deposit once the work is awarded.
|
| 2.1 |
The
offer must be submitted in 2 (Two) separate sealed envelopes
one containing technical, commercial terms, unpriced bid
and payment of earnest money while the other envelope containing
price bid. The sealed envelopes should be clearly marked
as per contents. Both the sealed envelopes should be put
in another single envelope. The envelope containing technical,
commercial, unpriced bid and earnest money will be opened
first. The price bids will be opened only after the bidder
has complied with all the terms and conditions and if the
offer is technically responsive. The price bid of the bidder
who has not fulfilled the terms and conditions of the tender
and whose offer is not technically responsive may not be
opened and considered at all.
|
| 3. |
Time
of Completion:
The work shall be started within 7 (Seven) days from the
date of receipt of work order/L.O.I. or the handing over
the site whichever is later and completed within 12 (Sixteen)
weeks there from.
|
| 4. |
Special
Conditions
|
| 4.1 |
Materials
and workmanship shall conform to relevant IS Specification
and drawings, if any, issued for the work, Instruction of
Engineer-in charge are to be followed in absence of IS Specifications
for any item.
|
| 4.2 |
Rate
quoted must cover all items of incidents, transport, conveyance,
taxes, octroi etc. for the completion of work.
|
| 4.3 |
Work
has to be carried out in a site along with other agencies
without affecting normal activities of GRSE.
|
| 4.4 |
Contractor
shall abide by the security regulations of GRSE for safe
custody and movement of men and materials as applicable.
Photo passes in prescribed proforma shall be arranged by
the contractor for the men working more than a fortnight
at a time.
|
| 4.5 |
Safety
measures such as using safety belts etc are to be adopted
while working overhead. Contractor will be responsible for
any damage caused by them to GRSE property.
|
| 4.6 |
One
full time responsible and qualified supervisor / representative
has to be posted at site during progress of the work.
|
| 4.7 |
All
rates shall be quoted on the tender schedule both in figures
as well as in words. In case of any discrepancy found between
the rate/amounts quoted in figures and words, the rate/amounts
quoted in words will be considered for acceptance.
|
| 4.8 |
Tenderer
shall initial all correction and sign with date on each
page of the tender. In case of any discrepancy the rate/total
value written in words shall be accepted.
|
| 4.9 |
The
quantities given in the schedule are approximate and may
vary as per actual requirement at site. Payment shall be
made on the basis of actual measurement of the work to be
certified by the Engineer-in-Charge.
|
| 4.10 |
Measurement
shall be made as per the relevant IS Code, except wherever
otherwise mentioned.
|
| 4.11 |
GRSE
reserves the right to split up the work to various contractors,
if found necessary and to restrict the items of the quantum
of work as per requirement and no claim on this account
will be admitted. In case of split up time frame will
be reduced and settled after discussions with contractor.
|
| 4.12 |
During
the pendency of the contract, the contractor will not employ
any Officer of GRSE without GRSE’s written consent, GRSE
reserves the right to terminate the contract in case of
breach of this stipulation.
|
| 4.13 |
Labour
|
| 4.13.1 |
The
contractor is required to pay all legal dues to the workmen
engaged by him, as per the laws in force. The relevant acts
which are to be complied with in this connection are contract
labour (Regulation & Abolition) Act 1979, P.F. Act,
1952. Bonus act 1965, ESI Act 1948. WB House Rent Allowance
Act 1974 & Gratuity Act 1972.
|
| 4.13.2 |
The
minimum wages paid to the contract labour/workmen shall
be in conformity with the Govt.’s direction in this regard.
|
| 4.13.3 |
In
the event of failure of the contract or to pay to the contract
labour/workmen his legal dues, GRSE will reserves the right
to deduct such due, from the final bill of the contractor
and arrange reimbursement to the concerned labour/workmen.
|
| 4.13.4 |
The
quotation shall be valid for acceptance for a period of
3(three) months from the date of submission.
|
| 4.14 |
No
claim for idle charge due to non-supply of any materials
or services or work fronts by GRSE or for any other reasons
will be entertained.
|
| 4.15 |
No
claim will be entertained due to sudden fluctuations of
rates of labour and materials, freights, taxes and duties
etc. at any stage.
|
| 4.16 |
Tenderers
are advised to inspect and examine the site and its surroundings
means of access to site and nature of work before submitting
the tender. No extra charges/claims subsequent of any misunderstanding
or otherwise shall be allowed.
|
| 4.17 |
Liquidated
Damages:
If the contractor fails to complete the work within the
stipulated time, the contractor shall be liable to pay GRSE
Liquidated Damages for delay and not by way of penalty,
a sum of 1 % of the value of work in respect of every week
of delay or part thereof, subject to a maximum of 10 % of
the value of the work executed by the contractor.
|
| 4.18 |
GRSE
reserves the right to cancel the works in case of poor materiel
supply, poor workmanship/progress and get the work completed
at risk and cost of the contractor.
|
| 4.19 |
Payment
Terms
|
| 4.19.1 |
The
contractor shall submit the bill in quadruplicate along
with measurement sheet in duplicate material reconciliation
statement with supporting SIRs / Challans for the materials
issued from GRSE Stores, if any and the bill format with
supporting documents.
|
| 4.19.2 |
90%
payment of the value of work done shall be made within 30
days of submission of bills after deduction of cost of materials
if any, issued by GRSE on recovery basis as per certificate
of Engineer-in-Charge, after satisfactory completion of
job. R/A Bills are payable only once in a month. Minimum
value of R/A Bills payable shall be Rs.3, 00,000/- (Rupees
three Lakhs only). Final Bill (90% payment) will be paid
after satisfactory completion of entire work.
|
| 4.19.3 |
Balance
10% of the value of the whole work inclusive of Earnest
Money, if any, which forms the Security Deposit shall be
released after satisfactory maintenance of the work for
a period of 12 (Twelve) months from the date
of completion.
|
| 4.20.1 |
Contractor
has to submit gate entry challans with quantities duly certified
by Gate Office for materials procedure for this work.
|
| 4.20.2 |
Working
Hours:
Contractor’s men will be allowed to work only during working
hours of GRSE. If work is absolutely required beyond working
hours including Sundays/Holidays special permission have
to be taken by contractor for each day. GRSE may or may
not giver permission for work beyond working hours for security
reasons. No claim of extension of time will be granted on
this ground.
|
| 4.20.3 |
All
the contractor’s men including the site in charge will wear
a red color cloth “Arm Band” of 6” in width with name of
the firm written on block letters on it. This arm band is
to be put on the left arm at the time of entry into GRSE
till the time they leave the factory premises.
|
| 4.20.4 |
General
Conditions:
The conditions of contract shall be the General Conditions
of contract works of Civil Engineering Construction and
Maintenance for GRSE Ltd. (herein-after called the General
Conditions). The General conditions of contract and Technical
Specification are available with Civil Engineering Department
for inspection. In so far as any of the conditions above
may conflict or are inconsistent with any of the General
Conditions, the Special conditions shall always prevail.
The conditions provide for sole Arbitration of Chairman/Managing
Director/GRSER Ltd. or his nominee for settlement of any
dispute on this work.
|
| 4.20.5 |
GRSE
do not bind them to accept the lowest or any tender or to
assign any reason(s) thereof.
|
| 4.20.6 |
ESI
Act:
The bidder must have own ESI Code No. and the same has to
indicate in techno commercial bid. The deposit receipts
are to be shown to GRSE during processing of bills.
|
| 4.20.7 |
If
any party does not respond to this enquiry without showing
acceptable reasons, GRSE may impose restriction of business.
|
| 4.20.8 |
The
contractor wherever required, should organize to forward
the relevant Bank Guarantee of schedule Bank, preferably
Nationalized Banks., in Banker’s sealed envelop directly
to General Manager (Finance), Corporate Finance, super scribing
the words ‘BANK GUARANTEE’
|
| 4.20.9 |
If
there is any conflict between the Tender Notice in
English and those in any other
|
| 4.20.10 |
VAT
Tax:
All contractors registered under VAT ACT will have to use
11 Digit TIN or Tax Payer’s Identification Number. Work
contractors registered under VAT ACT have to pay tax at
a compound rate of 2% on the entire contractual
transfer price, irrespective of quantum of contractual transfer
price. Once the contractor has exercised option for payment
of tax at compounded rate, it will be valid for one financial
year. The contractor opting for payment of tax at compounded
rate are not entitled to input tax credit and can not issue
tax in voices.
|
| 4.21 |
As
per the Official Secret Act 1923 of Ministry of Home Affairs,
Govt. of India, Police Verification Certificate of character
antecedents in respect of all employees of Contractors/Subcontractors
operating in GRSE Ltd., is required to be submitted by the
concerned contractors/subcontract before processing any
gate pass for their employees, failing which gate pass may
not be issued.
|
| 4.22 |
P.F.
Clause:
The Contractor has to indicate own PF Code No. as possessed
and show deposit Challans to GRSE during processing of bills.
|
| 4.23 |
Material:
Labour:
Material or all purpose for items involving both material
and labour the components of 80: 20 would be considered.
|
| 4.24 |
In
case of requirement, the said work may be splitted into
2 or 3 Contractors with L1 rates.
|
| 5. |
The
bidder who is not enlisted with GRSE yet, should furnish
the details of similar work executed in last one year, like
Purchase Order No., date, value, completion of certificate,
contact details like name, address, telephone no. of the
person under whose direct jurisdiction the work was executed
of similar work executed in last one year, audited annual
accounts statement of last three years for evaluation of
financial stability, details of infrastructures including
human resources available etc.
|
| |
For
Garden Reach Shipbuilders & Engineers Ltd. |
| |
(T.
S. Mukherjee) |
| |
Deputy
General Manager (ES) |
|
|
|
|