S N |
Tender No. |
Date of opening |
Description of
item/work |
Contract No. and Date |
Contractor’s Name |
Quantity (for supply
contract) |
Estimated cost (for
Engg./ Elect/ S&T/Mech.)
Rs |
Rate (for supply
contract) Tendered cost (for Engg./Elect /S&T/Mech.) |
Value of contract Rs |
Scheduled completion
date |
|
A |
B |
C |
D |
E |
F |
G |
H |
I |
J |
K |
|
1 |
10 of 2006-07 (SLT) |
25.05.06 |
Construction of
foundation and substructure and erection/launching of superstructure of
bridge no. 9 (3x12.2 m), 15(2x12.2 m), 30 (4x12.2 m) and minor bridges
from km 0.00 to 16.5 in connection with construction of new line in
Muzaffarpur- Sitamarhi section. |
ECR/CAO/Con/WT/320 Dated
19.06.06 |
Hindustan Steelworks
Construction Ltd.
Unit: Land Development Bank Building (3rd Floor), Budh Marg,
Patna- 800001. |
N.A |
7.49 Cr |
N.A. |
7.49 Cr |
18.12.06 |
|
2 |
11 of 2006-07 (SLT) |
25.05.06 |
Construction of
foundation and substructure and erection/ launching of superstructure of
bridge no. 17(2x12.2 m), 37(3x12.2 m),40 (2x12.2 m), 45(2x12.20 m) and
minor bridges from km 16.5 to 20.0 in connection with construction of new
line in Muzaffarpur- Sitamarhi section. |
ECR/CAO/Con/WT/319
Dated.19.06.06 |
Allied Infrastructures
& Projects Pvt Ltd. 2nd
and 3rd floor, P-16, Bentik Street, A.C. Mansion,
Kolkata-700001. |
N.A |
7.11 Cr |
N.A |
7.11 Cr |
18.12.06 |
|
3 |
14 of
2005-06 (Open) |
11.11.05 |
Flash butt welding of
52/60 Kg rails at site using Mobile Flash Butt welding plant for different
construction projects in East Central Railway". |
ECR/CAO/Con/WT/NIT/ 210 (Vol-I)
Dated.31.05.06 |
Royal Forgings (Pvt.)
Ltd.,
18, R.N. Mukharjee Road, Kolkata-700001. |
N.A |
15.97 Cr |
N.A |
15.97 Cr |
30.05.09. |
|
4 |
82 of
2004-05 (Open) |
27.04.05 |
Earth work in cutting,
filling, compaction, turfing, construction of minor bridges and other
associated works between Hazaribagh to Barkakana in connection with
construction of a new BG Rail line from Koderma to Ranchi Reach-XXV, Ch.km
104.100 to Km. 108.000. |
ECR/CAO/Con/WT/193/
1844
Dated.09.05.06 |
B.K.B Transport Pvt. Ltd.
New Road, P.O. Phusro Bazar
Dist. Bokaro 829144
|
N.A |
10.25 Cr |
N.A |
10.78 Cr |
08.05.08 |
|
5 |
17 of
2005-06 (Open) |
24.08.05 |
Earth work in cutting,
filling, compaction, blanketing, turfing, minor bridges and other
associated works between Rakesh Bagh and Rema station in connection with
construction of a new BG Rail line of Koderma-Giridih section (Reach–V,
Ch.43.00 Km. to 56.00Km.) |
ECR/CAO/Con/WT/224
Dated.15.05.06 |
Y.P.C-Dushad Construction
(JV), 3, Professor Colony, Yamuna
Nagar-135001, Haryana
|
N.A |
13.70 Cr |
N.A |
13.24 Cr |
14.01.08 |
|
6 |
45 of
2005-06 (Open) |
23.11.05 |
Earth work in cutting,
filling, compaction, turfing construction of minor bridges and other
associated works between Hazaribagh to Barkakana in connection with
Construction of a new BG Rail line from Koderma to Ranchi. (Reach–XXI,
Ch. Km 97.200 to Km 99.200) |
ECR/CAO/Con/
WT/248/2167
Dated.29.05.06 |
Highway & Hydel
Project Pvt. Ltd.,
Flat No.501, Om Sai Apartments, Anantpur, Ranchi. |
N.A |
9.26 Cr |
N.A |
7.74 Cr |
28.05.08 |
|
7 |
46 of
2005-06 (Open) |
23.11.05 |
Earth work in cutting ,
filling, compaction ,turfing construction of minor bridges and other
associated works between Hazaribagh to Barkakana in connection with
Construction of a new BG Rail line from Koderma to Ranchi. (Reach–XXII,
Ch. Km 99.200 to Km 101.200) |
ECR/CAO/Con/
WT/249/2618
Dated.22.06.06 |
Highway & Hydel
Project Pvt. Ltd.,
Flat No.501, Om Sai Apartments, Anantpur, Ranchi. |
N.A |
9.37 Cr |
N.A |
8.93 Cr |
21.06.08 |
|
8 |
63of
2004-05 (Open) |
27.04.05 |
Construction/
strengthening of 11 nos. major bridges between Miraj and Purnia stations
in connection with gauge conversion work of Saharsa Purnia section. |
ECR/CAO/Con/
WT/177/2227
Dated.31.05.06
|
Vasundhara Nirman Pvt.
Ltd.,
303, Adharshila complex, south Gandhi Maidan, Patna
|
N.A |
11.42 Cr |
N.A |
13.73 Cr |
30.08.07 |
|
9 |
02of
2005-06 (Open) |
25.05.05 |
Rebuilding of Bridge No. 4, construction of
New Major bridges at Km.64/1-2, Km 93/5-7 on pile foundation, RCC Box at
Km.45/11-12, Km.46/6-7, Km.59/7-8 and Km.61/13-14 of any other left over
bridges) on same alignment/permanent diversion, Jacketing of any left over
bridges and regirdering of Bridge No.18(4x18.30m) in Darbhanga-Sitamarhi
section in connection with gauge conversion of JYG-DBG-NKE section. |
ECR/CAO/Con/
WT/190/2225
Dated.31.05.06
|
Civtect (India) Pvt.
Ltd
73/29, Golf Club Road,
Kolkata-700033
|
N.A |
6.36 Cr |
N.A |
6.93 Cr |
30.04.07 |
|
10 |
74
of 2005-06 (Open) |
01.03.06 |
Construction of sub-structure of major
bridge no. - 7 ,7B-I and 8, construction of minor bridges and earth work
in filling/cutting in widening of bank, platform, level crossing and
trolley refuses between Narkatiaganj and Bhikhinathori stations in
connection with gauge conversion of JYG-DBG-NKE section. |
ECR/CAO/Con/
WT/278/2341
Dated.01.06.06
|
Sahil Construction
Company
Near Bus Stand
P.O. Chitrapur
Dist. Hazaribagh (Jharkhand) Pin-825101
|
N.A |
5.24 Cr |
N.A |
4.89 Cr |
31.08.07 |