Sub:
Corrigendum to Tender Notice No. 11/2009-10.
|
|
Ref:
This office letter of even no dated 14.10.09 & 03.11.09 (1st
Corrigendum).
|
|
Please read the
description of work of tender against Sl. No. 13 under the above
tender notice in the section of DEN(3)HWH as “CTR[S] of
existing 50/75 lbs. Rails on wooden sleepers by 90R/52Kg. rail
on SH/ST [NG] modified sleeper between Km. 21.5 to 26.5 = 5 Km.
and Km. 48.00 to 52.20 = 4.20 Km. on A-K [NG] Section under
SE[P.Way]/KWAE[NG] under AEN/KWAE” INSTEAD OF “CTS[S] of existing 50/75 lbs. Rails on wooden sleepers by
90R/52Kg. ril on SH/ST [NG] modified sleeper between Km. 21.5 to
26.5 = 5 Km. and Km. 48.00 to 52.20 = 4.20 Km. on A-K [NG]
Section under SE[P.Way]/KWAE[NG] under AEN/KWAE” as published.
|
All other terms and conditions of
all other tenders under the above tender notice shall remain
unchanged.
|
|
|
For Divisional Railway Manager,
|
|
|
Eastern Railway, Howrah.
|
|
|
|